Project 77
Construction
501 E 8th St, South Boston
Property address
501 E 8th St, South Boston, MA 02127
Scope of work
Code compliance
Stage
Closeout
Contract amount
$248,000.00
Estimated budget
$240,000.00
Awarded subcontractor
Old Colony Masonry (Masonry)
Scope start date
Oct 1, 2025
Contract signed date
Nov 1, 2025
Build start date
Dec 1, 2025
Target completion
Apr 15, 2026
Closeout date
May 1, 2026
Owner signature / date
Contractor signature / date
Generated 9/12/2026 — not a substitute for a signed original.